Chapter 5 Finishing @@@@@(Thermal Insulation of Home) @@1221
The
eighth week of construction.
It is a finish stage
As for the outside wall, the seal material was filled to the space. The outside wall construction was completed by this task. Kyokabe wall was painted on the inner wall which had given the processing of groundwork in the Japanese-style room, and hanging type slide doors [tsurito] were set up in the boundary with the next living room.
The construction seemed to have come to the stage of finish. The days when construction had been executed were half of this week.
iPainted
Kyokabe wall) (Fill the seal material between blue tapesB) [tsurito]
The ninth
week of construction.
Painter's work
Painters were supposed to paint the gable and under the roof outside of the wall. The eaves damaged were supposed to be painted free of charge as I had mentioned before. Arrived a painting contractor saw the recently painted roof. gPainted it by youIMoreover, you painted sealing coat!" He seemed to have been surprised.
However, he added, "When you need painting it again, the silicon paint is not goodh I am going to replaced the roof tiles next time. But we also had painted the surface of the mortal which had remained such the terrace side.
I asked my son to paint the eaves side mortal. I thought non-painted
eaves were looked shabby. At that time, the painter said, "Please use this
paint if you will paint more". Immediately, I made my son to paint eaves
that had not been painted yet.
iDented
and scratched eaves were painted by the painter) iPaintings the eaves
sidej@@
Monday
of the tenth week
Installation of Inner windows
@A window constructor came to our house and installed inner windows. There was one thing prevented from his installing the inner window.
Because the pillar in the living room had swollen with a longtime dewfall,
he cut down the swelling and put in the inner window. The dewfall easily
spoils @the pillar. @It is necessary to take care as well as the white
ant damage.
He finished installing all the inner windows till around five o'clock of the evening with taking only a little rest as lunchtime.
iPortrait
windowj
. The plasterer person corrected the irregular paint in the Japanese style room that my wife was pointing out on this day,@too.
Tuesday
of the tenth week
Gutter installation
Sheet metal workers came and the eaves gutter was installed by them. Till then, it was a hemicycle shape. However, they exchange it for the trapezoid one. .Capacity had grown.
(The
eaves gutter was installed.)
Wednesday of the tenth week
Insulation behind the shutter
door case
Insulation behind the shutter door cases were old 50mm fiber glass, because they only exchange those fiber glass where the mortal were peeled. So, the fiber glass in the wall where are covered by the shutter door case were old ones.
We decided to install the siding panels which were left over of the outside wall construction. As a result, some sounds from the outside seem to reduce.
iWe inserted the siding into the case.j
Friday
of the tenth week
Scaffold dismantlement
The day when the scaffold (work stand) was dismantled finally came. This day, a further trouble occurred.